Below you will find details on the development size & location as well as site plans, house styles, photographs, internal walk through videos, drone footage and a 360° walkthrough where available.
We purchased the site from Springfield Properties on 31 March 2021.
Springfield are our main contractor for the work and they started on site on 31 May 2021.
A total of 64 new homes for rent were delivered on the site which comprise a mixture of cottage flats and houses, designed for general needs, and also houses designed for both amenity and wheelchair use.
Overall completion of this new build development was acknowledged on 29th of February 2024. All 64 homes have now been allocated
DEVELOPMENT
Heathhall
Completion Date
February 2024
AREA
Dumfries & Galloway
HEATHHALL Walkthrough Video Dec 2022
An internal walkthrough in our Heathhall Development
HEATHHALL Progress Video NOV 2022
Check out our progress video from the Heathhall Development
HEATHHALL FLYOVER
A brief drone flyover of the site before works started.