Below you will find details on the development size & location as well as site plans, house styles, photographs, internal walk through videos, drone footage and a 360° walkthrough where available.
The site was purchased by the Association on 24 March 2021 and will provide a total of 72 new homes for rent.
Work was scheduled to start on site by the end of April 2021 with a contract period of 95 weeks to complete the project, resulting in a proposed handover date of July 2022.
The Association has appointed McTaggart Construction as their Design & Build contractor.
The new homes will provide a mix of general needs family housing as well as bungalows designed for elderly people and those with particular housing needs.
Work commenced on site on 12 April 2021, with overall completion date was March 2023.
A total of 72 new homes for rent are being delivered on site by McTaggart Construction.
The new homes will provide a mixture of general needs family housing, as well as bungalows designed for elderly people and those with particular needs.
DEVELOPMENT
West Byrehill – Kilwinning
Completion Date
28th March 2023
AREA
North Ayrshire